Water Source Evaluation

Project Type:
Water
Project Status: 
On Hold

Project, originally started in 2020, consists of analyzing and designing improvements needed at the Hegewald well to convert it from an emergency source to a permanent water source. Will evaluate the Rock Creek intake for needed improvements to improve performance.


Contract: Grayling Engineering $19.6k
Progress: 90% Complete
Budget: $19.6k / $3.5k Spent
Funding: $19.6k Water Fund
Planned Completion Date: October 31, 2021

Status Updates

June 2022 - The final tech memo was delivered in January, 2022. The cost estimate came in at close to $712,000. The City will continue testing water composition throughout the year to further inform design. The project is on hold until we obtain more data.

June 2021 - Working on cost-analysis for treatment options.