East Loop Road Waterline
Project consists of replacing a 6” AC waterline along Loop Rd. from Vancouver to Kanaka Creek Rd ahead of a street improvement project. It also cleans-up a valve cluster near Vancouver.
Contract: Odyssey Contracting, LLC $152k
Progress: Design 100% Complete
Budget: $162k / $156k Spent
Funding: Water Fund
Planned Completion Date: June 30, 2023
Status Updates
August 2023 - The project is completed and accepted by the City.
March 2023 - The contract has been awarded to Odyssey Contracting LLC for $152,072.40. The pre-construction meeting will be held on March 31st where a detailed schedule will be provided.
December 2022 - The project is budgeted for 2023 as the street portion of the project received a grant and will be funded in 2023. Bidding is anticipated for February 2023.
June 2021 - The project has been planned. Project on hold as other tasks are taking priority.