Lower Kanaka Creek Rd.

Project Type:
Streets/Transportation
Project Status: 
Completed
Completed Kanaka Underpass Bridge Replacement

Project consists of replacing the timber bridge at the Kanaka Underpass and widening the road as much as possible. There is a weight restriction on the bridge until the repairs can be completed.


Contract: N/A
Progress: 100% Complete
Budget: $20k Budget / $9k Spent
Funding: $20k Street Fund
Planned Completion Date: December 31, 2021

Status Updates

September 2021 - The road was closed on 7/29 due to safety concerns at the bridge. The decking was replaced by staff and was completed on 9/16.

June 2021 - Timber has been sourced and priced. Holding off on purchase.