West Vancouver Waterline Extension

Project Type:
Water
Project Status: 
On Hold

Project consists of extending a 6” main from Lasher to Rock Creek, improving fire flow, removing a section of 4” AC line and adding redundancy to the system.


Contract: TBD
Progress: Design 90% Complete
Budget: $385k / $0k Spent
Funding: $385k Water Fund
Planned Completion Date: December 31, 2026

Status Updates

December 2022 - The project is on hold due to other higher priority projects in process.

June 2021 - The project is being designed and will go out to bid in the spring. Construction will start in the summer and be completed by the end of the year.