Russell Avenue Improvements:

Improvements are currently underway to the lower section of Russell Avenue from Cascade Avenue to Second Street. The project will include road surface, sidewalk, storm water and waterline improvements.

 

 

 

Current Update:

6/16/2020

 

As of last Friday all of the overhead utility poles that were slated for removal were removed with the exception of one on the west side of Russell in Ash Alley. This pole is supporting another utility pole to the east and it’s removal is being coordinated via Centurylink with a projected removal timeline of “soon”. This week’s lookahead will see more sidewalk cement being poured in Ash Alley and lower Russell. Lower Russell road demolition will begin tomorrow one lane at a time. Ballast/gravel will be in place by the end of the day Friday and both lanes will be open for the weekend. Paving is scheduled for 6/24-6/25. Street lights are scheduled to be installed 6/22-25. Irrigation and landscaping is scheduled for 6/29-30. Items that need to be reworked/repaired (punch list items) will be addressed 6/30-7/2. The three week outlook has 7/2 as a date of completion. Keep your fingers crossed please!

 

Stay safe,
Karl Russell
City of Stevenson

You can find a list of all Russell Ave Improvement updates here.

 

Water and Wastewater Improvements:

Water and wastewater systems have been a primary focus for the Public Works Department. Staff has been working with stakeholders and the Department of Ecology for solutions to address high BOD levels and to plan for construction of aging infrastructure. Click here to be taken to our News page for more information on recent activities.