Paving will begin today at 9:00 A.M. Hopes are to get the Westbound lane of 1st St. and all of Russell between 1st and 2nd Street paved. Temporary striping will be put down tomorrow. Russell St. between 1st and 2nd street will be open for traffic Thursday afternoon or Friday depending on the progress and drying of the temporary striping. Curb and sidewalk prep and pouring are ongoing on lower Russell. When it comes time for paving on lower Russell one lane of traffic will remain open at all times.

 