Last week’s progress was slowed by weather. The waterline between 1st and Railroad Street was installed and will be tied into the existing water system by the end of today. Some concrete was poured in front of the post office and on the east side of Russell, however not as much as anticipated.

 

This week’s progress will consist of curb and sidewalk demo and prep and storm drain installation between 1st and Railroad Street. Concrete will be poured as weather allows. We are still waiting on communication lines to be taken off of the power poles. I have been told that hopefully lines can come off the poles in two weeks. There are concrete panels on the west side of Russell that cannot be poured until the poles are removed. Paving of Russell between 2nd and 1st has been delayed until June 4th. This is due to weather and the availability of the certain asphalt mix that is required. Overall, the project is a month ahead of schedule.

 

Stay safe,
Karl Russell
City of Stevenson