This weeks construction will consist of:

  • Westside sidewalk pouring
  • Eastside sidewalk forming
  • Weather dependent Eastside sidewalk pouring.
  • “Hot tap” for water main on South Russell Street
  • Storm water catch basins South Russell

There will be three spots on the east side of Russell Street where sidewalk will not be able to be poured until power poles are removed. They are scheduled to be removed mid May. Please keep in mind that the sidewalk pouring is ahead of schedule. Once the poles are removed concrete will be poured in these areas. A temporary ramp will be installed in front of the post office during sidewalk pouring to allow customers access however delays of a few minutes are anticipated while concrete is being worked prior to the ramp being set in place. Discussions of a Sunday pour maybe an option that is still being discussed.  Asphalt removal from 2nd St. to 1st will begin Monday.
Stay safe,
Karl Russell
City of Stevenson